Week 0: pick one operating question
Become a connected enterprise is not a rollout. Cut unplanned downtime on Line 4 and 5 is. See at-risk inbound on the west corridor is. The first dashboard should answer that question for the people who already own it.
Weeks 1 to 3: constraints, not workshops for their own sake
Inventory the devices, protocols, networks, and SOP limits. Name the users who will be paged. Decide what happens when the WAN dies. If this work is skipped, the build phase becomes archaeology.
Weeks 4 to 8: a thin live slice
Connect the pilot assets, buffer at the edge, land a role view, and run alerts in shadow if needed so you can kill noise before it pages people. Success is an operator using the screen during a real shift, not a steering-committee demo.
Weeks 9 to 12: hygiene and a second unit
Fix thresholds, acknowledgement, and the two reports leadership actually asked for. Then clone the pattern to a second line, yard, or corridor. Scale is repetition of a believed slice, not a bigger launch party.
What not to promise in week one
Do not promise a full digital twin, a global command centre, and AI insights on an unmapped tag list. EILM solutions exist so the first slice is a product path on one platform - unless the workflow truly requires custom engineering.